NORTHFIELD TOWNSHIP                      
PSB CONSTRUCTION COSTS                      
YEARS ENDED JUNE 30, 2000, 2001, 2002 & 2003                      
                       
                       
                       
DESCRIPTION             2000             2001             2002           2003         TOTALS  
                       
AMERICAN INTERIORS                      68,631.39          68,631.39  
AMERICAN TITLE            5,000.00            552.00                    5,552.00  
ANN ARBOR ARCHITECTS        108,808.07      180,073.08                288,881.15  
BODMAN LONGLEY            5,029.65          9,465.70              29,163.70          43,659.05  
CDPA ARCHITECTS            62,724.36        306,005.53          61,320.91        430,050.80  
DTE ENERGY / UTILITIES                    1,391.47          12,597.78          13,989.25  
INSIGHT ENVIRONMENTAL            1,000.00          1,000.00                    2,000.00  
LAND PURCHASE          247,878.50                247,878.50  
MCM GROUP - INSURANCE                      33,571.00          33,571.00  
NEEDERMAN CONSTRUCTION                      54,473.91          54,473.91  
NFTS - TAX, SEWER PERMIT                579.96              10,500.00          11,079.96  
O'NEAL CONSTRUCTION - POLICE / FIRE BUILDING  
 
       26,076.30      2,840,733.62      3,170,274.58      6,037,084.50  
OTHER              640.00                3,638.20          29,103.17          33,381.37  
TETRA TECH - ENGINEERING                    1,653.83                1,653.83  
STATION #2 - O'NEAL & OTHERS            98,030.50            1,928.09              99,958.59  
TREE REMOVAL                    8,300.00                8,300.00  
VENTURE SPECIALTY PRODUCTS - FLOORING                      76,785.00          76,785.00  
WASHTENAW CO - INSPECTIONS                      427.10                  427.10  
WASHTENAW ENGINEERING              5,000.00                    5,000.00  
XFER INTERNATIONAL - PHONE SYS                      22,301.26          22,301.26  
                       
TOTAL CONSTRUCTION COSTS        120,477.72      631,380.40      3,164,077.84      3,568,722.70      7,484,658.66  
                       
PROFESSIONAL FEES                  92,917.60              92,917.60  
BOND DISCOUNTS                100,898.00            100,898.00  
AGENT FEES                      300.00                  300.00  
                       
TOTAL COST OF PUBLIC SAFETY BUILDING                      7,678,774.26  
                       
                       
                       
O'NEAL (Construction) BREAKDOWN               Architects' Fees:      
                 $718,931.95      
BILLINGS BEFORE CONTRACT          40,129.50                  
PUBLICATIONS            1,703.00                  
CONTRACT BILLINGS TO DATE      5,940,323.00                  
CONTINGENT BILLING          54,929.00                  
                       
TOTAL      6,037,084.50                  
                       
                Costs not including O'Neal.  
Cost overrun beyond $6.8 million bonded        878,774.26           1,447,574.16